Status terminology work Daglig borerapport project meeting May 23d 2006
Agenda 1.Status •Begrepsdefinisjoner •XML-koding •samarbeid med POSC 2.Testing/pilotering. 3.Økonomi 4.Lunsj
Current Plan DateTask Project meeting (1-06) Daily Drilling Report Terminology based on CDRS suggested Meeting Hydro Meeting Statoil Meeting ConocoPhillips Meeting BP Start updating according to feedback from meetings and review Project meeting (2-06) Terminology based on CDRS complete XML kick off, POSC, Capgemini, project participants (Originally 2-3 days) Teleconference with POSC Project meeting (3-06) 16.06Terminology updated according to new requirements from PSA/NPD 31.07XML schemas complete 01.08Start Pilot, and adjust 31.08Project meeting (4-06) – decision to recommends implementation?
Terminology & XML- Status 1.Terminology based on “old” CDRS completed and added to ISO reference data library 2.Requirements from NPD/PSA changed •Terminology based on new requirements from NPD/PSA in progress – ETC June 16 th
Terminology & XML- Status 1.Terminology based on “old” CDRS completed and added to ISO reference data library 2.Requirements from NPD/PSA changed •Terminology based on new requirements from NPD/PSA in progress – ETC June 16 th
Status XML Schema Daglig borerapport
Status •4 av 17 delrapporter •Basic information •Status •Pore pressure •Operation / Mode •Workshop internt og med POSC •Uke 22, workshop for nye delrapporter
Positive erfaringer •XML elementene har referanse til begrepsapparaet. •Prosjektgruppen positiv til delrapportene •POSC positive til arkitektur og struktur
Issues •Nye begreper/krav dukker opp •Mapping av begreper mot WITSML er tidkrevende •XML elementer har referanse til RDL, men RDL har ikke publisert begrepene -> etterarbeid.
Rapport - hovedelementer
Operation/mode
Pilotering Daglig borerapport
Pilot •Vi trenger rigger (utsendere av XML) og selskaper (mottagere av XML) som kan bli med på test. Det beste hadde vært å kunne bruke en rig fra hvert av de avsendende systemene (4 stykker) samt OD/Ptil.